Capital work done vs plan
39% of planned capital spending carried out
11.3 pt Falling
Down 11.3 points in a year.
Who decides what
Main decision-maker: City of Victoria Council Show all
| Body | What it decides | Law or bylaw | Last decision | Next decision |
|---|---|---|---|---|
| City of Victoria Council | Adopts the financial plan by bylaw each year, then sets property tax rates by bylaw before May 15. | Community Charter, s. 165 Community Charter, s. 197 | Five Year Financial Plan Bylaw, 2026 (No. 26-040) and 2026 tax rates adopted May 7, 2026 | 2027 financial plan, then tax rate bylaw before May 15, 2027 |
Councils: last general local election October 17, 2026; next on October 19, 2030, the third Saturday of October set by the Local Government Act, s. 52.
The first row is the main decision-maker. Each row says what a body decides and links to the law, order or bylaw that gives it that role. It does not say who caused a change: markets, households and other governments also move these numbers. Who decides what, for every measure · How we choose
Over time
2025 Of planned capital spending carried out, by year
- 39% of planned capital spending carried out
Show the numbers as a table
| Period | Value |
|---|---|
| 2025 | 39% |
| 2024 | 50% |
In plain words
Spending on new and replaced City assets (buildings, roads, pipes, equipment) in the year, as a share of the amount in the City’s financial plan.
How we decide “Falling”
The change is 22.4% of the earlier value, at or above the 5% threshold.
2025: $64,167,813 acquired against $164,272,000 in the financial plan (39.1%). 2024: $77,224,466 against $153,162,000 (50.4%), from the 2024 annual report.
Outcome measures read Better, Worse or About the same; published government targets read Ahead of, On or Behind target; value-judgement measures read Rising, Falling or Steady in a neutral colour. A change smaller than the agency's own margin of error, or otherwise smaller than 5% of the earlier value, is About the same (or Steady). No change is calculated across a marked break in a series. The rule.
Keep in mind
Why it matters. It compares what the City planned to build or replace with what it did. Shown for context, without a better or worse label.
- Both figures are the line “Acquisition of tangible capital assets” in the City’s audited Statement of Change in Net Financial Assets: the Financial Plan column and the actual column.
- Capital work not done in the year is usually carried forward to later years.
- The 2025 report restates 2024 at $73,457,247; the 2024 report showed $77,224,466. Each year is read from its own report here.
Which places
Area: City of Victoria
The City of Victoria municipality only, all neighbourhoods.
Included
- All City of Victoria neighbourhoods, including Downtown, James Bay, Fairfield, Fernwood, Oaklands, Hillside/Quadra, North Park, Burnside, Victoria West, Rockland, Jubilee and Gonzales
Not included
- Saanich, Oak Bay, Esquimalt, Langford and every other municipality in the region
Official definition
How the agency describes it: City of Victoria (municipality).
How we got it
This number is published by the agency as shown; it is not calculated here. The script reads it from the agency’s own document and refuses to show it unless the expected text is found.
Licence and credits
This figure is public but not under an open licence: the agency publishes it for anyone to read, and it is shown here with credit and a link to the agency’s terms. About licences.
- Licence
- Public data, not under an open licence. Used with attribution. Agency’s terms of use
- Updated by agency
- Yearly (audited report published mid-year); latest release Jul 17, 2026
- Retrieved
- Nov 11, 2026, 8:45 PM B.C. time
Source: City of Victoria, Annual Report 2025, Statement of Change in Net Financial Assets. Public document, used with attribution; not endorsed by the publisher.
Inputs and results
Inputs are money, staff or decisions; results are what services delivered. One does not prove the other moved. Kinds of measure