Capital work done vs plan

Area: City of Victoria Calendar year 2025

39% of planned capital spending carried out

11.3 pt Falling

Down 11.3 points in a year.

Who decides what

Main decision-maker: City of Victoria Council Show all
Who decides what: Capital work done vs plan
BodyWhat it decidesLaw or bylawLast decisionNext decision
City of Victoria CouncilAdopts the financial plan by bylaw each year, then sets property tax rates by bylaw before May 15.Community Charter, s. 165
Community Charter, s. 197
Five Year Financial Plan Bylaw, 2026 (No. 26-040) and 2026 tax rates adopted May 7, 20262027 financial plan, then tax rate bylaw before May 15, 2027

Councils: last general local election October 17, 2026; next on October 19, 2030, the third Saturday of October set by the Local Government Act, s. 52.

The first row is the main decision-maker. Each row says what a body decides and links to the law, order or bylaw that gives it that role. It does not say who caused a change: markets, households and other governments also move these numbers. Who decides what, for every measure · How we choose

Over time

2025 Of planned capital spending carried out, by year

  • 39% of planned capital spending carried out
Line chart, 2 periods from 2024 to 2025. Capital work done vs plan: starts at 50% of planned capital spending carried out (2024), ends at 39% of planned capital spending carried out (2025); highest 50% of planned capital spending carried out (2024), lowest 39% of planned capital spending carried out (2025). Every value is in the table.0%20%40%60%2025202439%50%2024: Capital work done vs plan: 50% of planned capital spending carried out2025: Capital work done vs plan: 39% of planned capital spending carried out
Line chart, 2 periods from 2024 to 2025. Capital work done vs plan: starts at 50% of planned capital spending carried out (2024), ends at 39% of planned capital spending carried out (2025); highest 50% of planned capital spending carried out (2024), lowest 39% of planned capital spending carried out (2025). Every value is in the table.0%20%40%60%2025202439%50%2024: Capital work done vs plan: 50% of planned capital spending carried out2025: Capital work done vs plan: 39% of planned capital spending carried out

Tap or drag on the chart to read any year.
Show the numbers as a table
Capital work done vs plan, City of Victoria (newest first)
PeriodValue
202539%
202450%

In plain words

Spending on new and replaced City assets (buildings, roads, pipes, equipment) in the year, as a share of the amount in the City’s financial plan.

How we decide “Falling”

The change is 22.4% of the earlier value, at or above the 5% threshold.

2025: $64,167,813 acquired against $164,272,000 in the financial plan (39.1%). 2024: $77,224,466 against $153,162,000 (50.4%), from the 2024 annual report.

Outcome measures read Better, Worse or About the same; published government targets read Ahead of, On or Behind target; value-judgement measures read Rising, Falling or Steady in a neutral colour. A change smaller than the agency's own margin of error, or otherwise smaller than 5% of the earlier value, is About the same (or Steady). No change is calculated across a marked break in a series. The rule.

Keep in mind

Why it matters. It compares what the City planned to build or replace with what it did. Shown for context, without a better or worse label.

  • Both figures are the line “Acquisition of tangible capital assets” in the City’s audited Statement of Change in Net Financial Assets: the Financial Plan column and the actual column.
  • Capital work not done in the year is usually carried forward to later years.
  • The 2025 report restates 2024 at $73,457,247; the 2024 report showed $77,224,466. Each year is read from its own report here.

Which places

Area: City of Victoria

The City of Victoria municipality only, all neighbourhoods.

Included

  • All City of Victoria neighbourhoods, including Downtown, James Bay, Fairfield, Fernwood, Oaklands, Hillside/Quadra, North Park, Burnside, Victoria West, Rockland, Jubilee and Gonzales

Not included

  • Saanich, Oak Bay, Esquimalt, Langford and every other municipality in the region

Official definition

How the agency describes it: City of Victoria (municipality).

How we got it

This number is published by the agency as shown; it is not calculated here. The script reads it from the agency’s own document and refuses to show it unless the expected text is found.

Licence and credits

This figure is public but not under an open licence: the agency publishes it for anyone to read, and it is shown here with credit and a link to the agency’s terms. About licences.

Licence
Public data, not under an open licence. Used with attribution. Agency’s terms of use
Updated by agency
Yearly (audited report published mid-year); latest release Jul 17, 2026
Retrieved
Nov 11, 2026, 8:45 PM B.C. time

Source: City of Victoria, Annual Report 2025, Statement of Change in Net Financial Assets. Public document, used with attribution; not endorsed by the publisher.